Vegetation and a low fence adjacent the Mile End crossing loop partially obscured the view that the crew of train 2MP9 had of the empty flat wagons at the rear of train 2MP1.
Debris originating from the starter failure was not contained by the starter casing and severed the number one engine B-sump oil scavenge pipe.
There were no formal systems in place to manage the accepted practice of Protection Officers leaving a work site to return a Track Warrant and Train Staff, prior to ceasing works, off-tracking and ensuring the line was clear. This practice led to the informal delegation of responsibility for ensuring the track was clear to others at the work site.
Reporting and communications were not carried out in accordance with Sydney Trains rules and procedures, so that key employees in the Rail Management Centre received delayed and/or partial information and allowed the train to continue in service.
Key staff had not been trained in Rail Resource Management.
Drivers are desensitised to the wheel slip protection indicator light activations through its regular activation in response to momentary losses of adhesion. This, coupled with the inadequate warning provided by the TMS, may result in delayed reaction in response to activations that need driver intervention.
The lack of an appointed Officer in Charge of the incident site prior to the arrival of an Incident Rail Commander led to a fragmented response with no single employee having a recognised leadership role on site.
The Flight Crew Operating Manual procedure for crew comparison of the calculated Vref40 speed, while designed to assist in identifying a data entry error, could be misinterpreted, thereby negating the effectiveness of the check.
The applicability of a general requirement to conduct aviation risk assessments for complex, new, unusual or irregular activities was open to interpretation.
The scheduled ultrasonic tests conducted in November 2013 on the 80 lb/yd rail between Northgate and Alice Springs had been ineffective in detecting and quantifying the significant defects present at 1036.541 km and 975.244 km locations.
Contrary to the requirements of procedure IN-PRC-020, GWA had not established a list of specific locations known to have an increased likelihood of failure, such that particular attention may be applied in those locations during inspections.
The placement of the insulated rail joints adjacent to signal DYN150 was not in accordance with the ARTC engineering procedure ESC-07-01.
The practice of using a third party (the shunt planner) to facilitate communication between Network Control Officers and train drivers at the Melbourne Freight Terminal prevented an effective response to the emergency.
Track defect monitoring and reporting was not being conducted as specified in the Westrail Narrow Gauge Mainline Code of Practice, limiting the awareness of the deteriorating track condition and the need for reassessment of track operating limits.
The poor condition of Royal Pescadores’ anchoring equipment was indicative of inadequate maintenance. The shipboard management team were not aware of the equipment’s maintenance history nor able to provide relevant documents from the ship’s planned maintenance system.
The International Association of Classification Societies (IACS) recommendation for having a means of slipping the anchor cable bitter outside the chain locker had not been provided on board Royal Pescadores. Further, the ship’s classification society, ClassNK, does not consider that the IACS recommended slipping arrangement is necessary for reducing safety risk.
While the Fremantle vessel traffic service (VTS) operational procedures were aimed at having precautionary measures in place for adverse weather conditions, the triggers specified in the procedures only referred to BoM-issued severe weather and gale warnings. As no wind speed limits were specified, the gale force winds experienced at Fremantle throughout the early hours of 8 May did not trigger the VTS procedural responses until 0600 – after the receipt of BoM-issued warnings.
The rail transport operator (GWA) had not maintained sufficient oversight of the activities of the rail infrastructure manager (Transfield Services), allowing the track to deteriorate to a level where trains could not be reliably run in a safe manner.
V/Line’s process for the inspection of level crossing sighting did not provide explicit instructions for the identification and removal of problem vegetation.
The Pacific National freight loading manual, and application of it, was ineffective at preventing load
shift with rod-in-coil product.