What happened

On 11 August 2011, a scheduled Melbourne to Sydney Express Passenger Train (XPT) partially separated as it passed over a dip in the track near Broadmeadows, Victoria. The train suffered a total loss of power and was unable to continue its journey.

What the ATSB found

The ATSB found that the tail pin in the draft gear between the lead power car and first carriage failed as a result of a brittle overstress fracture that was initiated by fatigue cracking. Recent routine ultrasonic testing had not detected the presence of the fatigue crack and post incident material testing established that the mechanical properties of the tail pin were below the required standard.

Following this incident, the ultrasonic testing procedure was revised to improve the detection of smaller cracks in the tail pin. However, the separation of another XPT near Seymour, Victoria, on 1 August 2012 in similar circumstances highlighted the fact that the ultrasonic testing regime was still not detecting all small fatigue cracks in critical areas of the tail pin.

This investigation did not examine how the track irregularities near Broadmeadow may have contributed to the partial separation of train ST24, why the track condition deteriorated significantly in the 6 weeks between when it was last rehabilitated and the day of the partial separation or why the inspection and maintenance regimes in place at the time did not detect the deterioration in track conditions. These issues will be considered as part of the broader safety issue investigation RI-2011-015 Safety of rail operations on the interstate rail line between Melbourne and Sydney.

What's been done as a result

A new batch of tail pins has been manufactured to an upgraded standard which includes improved quality control and acceptance testing and RailCorp, the operator of the XPT fleet, is currently in the process of fitting these new tail pins. RailCorp has also further revised the tail pin inspection regime with the aim of improving its effectiveness.

Safety message

It is important that components are fit for purpose and meet the appropriate requirements for service and that inspection regimes are effective in providing assurance of continuing equipment reliability.

Download Final Report
[ Download PDF: 3.88MB]
 
 
 
 
 
 

To download, click the link, then right-click and select Save As.

Copyright in material obtained from other agencies, private individuals or organisations, belongs to those agencies, individuals or organisations and should be credited accordingly.

 

Safety issues

RO-2011-012-SI-01 - RO-2011-012-SI-02 -  

XPT tail pin acceptance

RailCorp’s acceptance testing regime for tail pins did not identify that the tail pins stamped BU 06 04 were below standard and, hence, not suitable for service.

Safety issue details
Issue number:RO-2011-012-SI-01
Who it affects:Operators of trains with this arrangement of tail pin
Status:Adequately addressed


 

XPT tail pin testing

The method used to ultrasonically test the tail pins in-situ was not reliable and resulted in small fatigue cracks going undetected.

Safety issue details
Issue number:RO-2011-012-SI-02
Who it affects:Operators of trains with this arrangement of tail pin
Status:Adequately addressed

 
General details
Date: 11 August 2011 Investigation status: Completed 
Time: 0858 EST  
Location   (show map):Near Coolaroo  Investigation type: Occurrence Investigation 
State: Victoria Occurrence type: Rolling Stock Irregularity 
Release date: 26 April 2013  
Report status: Final Occurrence category: Incident 
 Highest injury level: None 
 
Train details
Train registration: ST24 
Type of operation: Scheduled interstate passenger service 
Damage to train: Minor 
Departure point:Melbourne, Vic
Destination:Sydney, NSW
 
 
 