While ARTC had a process for monitoring its maintainers when carrying out inspections and rectifications, it was unable to provide evidence of these activities being conducted.
ARTC is taking the following safety action in response to operations asset services assurance issues identified in the draft report, as well as an internal assurance audit:
Once implemented, these actions address both findings, with the first and second line of defence assurance functions working to ensuring front line staff are entering data into the asset management system as per procedures, and information on track condition is being adequately reported to support the decision support platform.
Meanwhile, clear audit procedures will allow audits to inform the business where improvements are necessary, as they are intended.
The ATSB has scheduled follow-up to review the Asset Integrity Second Line of Defence audit procedure roll-out for September 2026.