| Safety issue description |
Safety controls were ineffective in mitigating against a train arriving at Ballarat Railway Station travelling at excessive speed and being unable to stop before colliding with the crossing gates closed against rail traffic. |
|---|---|
| Issue number | RO-2020-007-SI-01 |
| Issue owner | V/Line |
| Transport function | Rail: Passenger - regional |
| Issue status | Closed – Adequately addressed |
| Date issue released | 28/10/2022 |
| Issue status justification |
The ATSB is satisfied that the action taken by V/Line has reduced the risk of this safety issue. |
| Action type | Proactive action |
|---|---|
| Action number | RO-2020-007-PSA-01 |
| Organisation | V/Line |
| Action description |
V/Line advised the ATSB of the following interim safety actions:
The ATSB is aware that at time of publishing there remained ongoing dialogue with stakeholders regarding the level crossing configuration. While the described interim safety actions taken by V/Line close this safety issue, any subsequent changes and controls reside with the rail operator. |
| Action status | Closed |