Safety issue

Safety issue description

Post-incident inspection of the derailment site identified a number of factors that increased the risk of a derailment in the refuge and main line. ARTC’s maintenance activities had identified some but not all of these factors prior to the derailment.

Issue number RO-2019-010-SI-02
Issue owner Australian Rail Track Corporation
Transport function Rail: Infrastructure
Date issue released 07/05/2020

Safety action

Action type Proactive action
Action number RO-2019-010-NSA-001
Organisation Australian Rail Track Corporation (ARTC)
Action date 07/05/2020
Action description

Safety action taken: ARTC undertook restorative work following the derailment and repaired the section of track.

ATSB response

The ATSB notes that the action taken will addresses the immediate safety issue, but does not resolve the underlying factors that contributed to the safety issue.

Action status Released