| Safety issue description |
Sydney Trains' control of the access and egress to the project worksite did not ensure that all workers entering the worksite were identified and received an induction. |
|---|---|
| Issue number | RO-2018-021-SI-01 |
| Issue owner | Sydney Trains |
| Transport function | Rail: Passenger - metropolitan |
| Issue status | Closed – Partially addressed |
| Date issue released | 30/06/2020 |
| Issue status justification |
The ATSB notes the safety action taken identified and implemented additional risk controls that reduce the likelihood of the safety issue arising. The residual risk has been assessed as low as reasonably practicable at this point in time. Advances in technology associated with rail safety worker safety may reduce the residual risk further into the future. |
| Action type | Proactive action |
|---|---|
| Action number | RO-2018-021-NSA-027 |
| Organisation | Sydney Trains |
| Action date | 30/06/2020 |
| Action description |
On 31 March 2021, Sydney Trains advised that the following actions have been taken in response to safety issue:
|
| ATSB response |
The ATSB notes the safety action taken in response to the safety issue is expected to reduce the likelihood of the safety issue arising. |
| Action status | Closed |