| Safety issue description |
V/Line did not have a documented detailed process for inhibiting and reinstating level crossing protection equipment. |
|---|---|
| Issue number | RO-2018-015-SI-01 |
| Issue owner | V/Line |
| Transport function | Rail: Passenger - regional |
| Issue status | Closed – Adequately addressed |
| Date issue released | 08/10/2019 |
| Issue status justification |
The ATSB is satisfied that the safety action taken by V/Line addresses the safety issue. |
| Action type | Proactive action |
|---|---|
| Action number | Missing number |
| Organisation | V/Line Pty Ltd |
| Action date | 08/10/2019 |
| Action description |
V/Line has developed and issued new specific procedures related to the task of inhibiting and reinstating level crossing equipment and conducted training for relevant employees in these procedures. |
| Action status | Closed |