Safety issue

Safety issue description

The existing standards stipulated minimum clearances between trains and platforms but did not consider the effect of the resulting gaps with respect to safe accessibility. 

Issue number RO-2014-005-SI-03
Issue owner Metro Trains Melbourne
Transport function Rail: Passenger - metropolitan
Issue status Closed – Adequately addressed
Date issue released 27/04/2016
Issue status justification

MTM has developed a design practice note to address safety issue.

Safety action

Action type Proactive action
Action number RO-2014-005-NSA-032
Organisation Metro Trains Melbourne
Action date 13/08/2016
Action description

For existing platform renewal, MTM is implementing the requirements of the ‘design practice note’ (DPN). This document provides guidelines on the permissible construction tolerances applicable to platform renewal works.

ATSB response

Adequately addressed.

Action status Closed - Action Taken