Final report
Report release date: 29/06/2007
Executive summary
At approximately 06441 on 2 June 2006, the crew of Interail freight service 5MB7 reported that their train had derailed while traversing the No. 3 points located at the Melbourne end of the Benalla crossing loop. Two locomotives and 19 wagons derailed, 16 wagons sustained major damage. Two track machines stabled in a cripple road2 adjacent the crossing loop were heavily damaged. A Victorian Railway Institute Hall near the site also sustained severe structural damage.
There were no serious injuries to the crew of the locomotive or the operators of the track machines. The train drivers were however taken to hospital for observation and treated for shock. There is no evidence to suggest that there were any medical or toxicology issues that affected the performance of either the driver or the co driver.
There were no defects identified with the signalling system. The signalling system was regularly maintained in accordance with applicable maintenance standards and there was no history of signalling abnormalities
As a result of its investigation the ATSB concluded that the factors which contributed to the derailment of train 5MB7 on the 2 June 2006 were:
- The driver was not expecting to cross a train at Benalla and thus assumed that he was being routed through the main line.
- The driver probably failed to correctly interpret and then respond to signal ES6377. As a result he was unable to slow the train to a safe speed for negotiating the facing points.
- The driver responded some 14 seconds beyond the available sighting point of No. 2 Signal. Had he responded earlier he could have slowed the train and potentially reduced the consequences of the derailment.
- Two-driver operation is a primary defence employed by Interail in guarding against unintended driver actions, the failure of the co-driver to look for and then validate/respond to the signal aspect displayed by signal ES6377 and No. 2 Signal was a clear breakdown in this defence and probably a contributing factor in the derailment.
- The driver and co-driver were both probably in a state of degraded arousal/vigilance when they passed signal ES6377 and while approaching No. 2 Signal.
Safety actions recommended include a review of crew resource management strategies, examination of mentoring responsibilities, and improving processes for the regular re-certification of drivers.
__________________________________
- All times throughout this report are Eastern Standard Time (EST). As times from various sources differ marginally, all times have been referenced to the Adelaide CTC event logger then adjusted by 30 minutes to correct for EST.
- Cripple Siding - The short section of track located off the Benalla crossing loop, used for storing disabled trains, rollingstock and track maintenance machines.
Occurrence summary
| Investigation number | 2006005 |
|---|---|
| Occurrence date | 02/06/2006 |
| Location | Benalla |
| State | Victoria |
| Report release date | 29/06/2007 |
| Report status | Final |
| Investigation type | Occurrence Investigation |
| Investigation status | Completed |
| Mode of transport | Rail |
| Rail occurrence category | Derailment |
| Occurrence class | Accident |
| Highest injury level | Minor |
Train details
| Train number | 5MB7Q |
|---|---|
| Type of operation | Freight Train |
| Departure point | Melbourne, Victoria |
| Destination | Brisbane, Queensland |
| Train damage | Substantial |