Rail safety issues and actions

Shear key installation

Issue number: RO-2016-001-SI-01
Who it affects: Rail Infrastructure Managers (RIMs)
Issue owner: Australian Rail Track Corporation (ARTC)
Operation affected: Rail: Infrastructure
Background: Investigation Report RO-2016-001
Date: 25 March 2019

Safety issue description

The shear key was not installed in accordance with the geotechnical engineer’s specification with respect to the following:

a) It did not include a cross-drain.

b) Its width was less than the specified width.

Proactive Action

Action organisation: Australian Rail Track Corporation
Action number: RO-2016-001-NSA-011
Date: 25 March 2019
Action status: Closed

Since the derailment of train WG713, ARTC has:

  • Completed a review of its civil and track standards and reinforced the importance of drainage in areas with a degraded formation to its track and civil staff
  • Completed reconditioning of the track formation at the incident location in Denman.

ATSB response:

The Australian Transport Safety Bureau notes the response provided and is satisfied with the action taken by ARTC.

Current issue status: Adequately addressed